Not alot has happened in the past fortnight!

Most of the scaffolding has been taken down and removed from site. Here are some pictures from last week:





After speaking with our SS yesterday, it turns out that the delay has been caused by the roof guys, as they requires scaffolding to return to site so that they can complete the roof over the garage. The scaffolding that they normally use is not enough, so there is a bit of a stand off occurring at the moment until this can be arranged! Extremely annoying, as the scaffold was only taken away during the week and the fact that we have lost at least a week with no activity.

This should hopefully be resolved this week. We should also see the air con and electrical rough in happen next week, all going well.