Saturday, December 12, 2009

Gyprock to Start 14/12

After not a lot of action in the week post my last update a fortnight ago, last week was a hive of activity on site!











The final touches to the roof, as well as the eaves and cladding have been completed last week by the carpenters. Insulation was also installed in readiness for the gyprocker’s to start this week.

We also had a meeting on site with our SS to sort out some of the issues that we have, as well as the issues from our independent inspection that we had done. The good news is that all of the issues raised have been fixed, and we are ready to move forward. He also shared with us the Tyrell’s report and the private certifiers frame report, all of which passed with a few minor issues to be addressed.

With a bit of luck, we should have all of our gyprock done and stair case installed and be at lock-up before Christmas. All of this will depend on the availability of the carpenters prior to Christmas, so here’s hoping all goes well.

Cheers,

CMET

2 comments:

NPGE said...

Wow it is all looking fantastic, it is soo good to see so much progress

CMET said...

And with the plaster this week, it makes it feel even more like our new home! Alot is on this coming week, so test will be if it all gets done before the close down.

How is everything going with yours?