Saturday, September 5, 2009

Post Slab Week

Not a huge amount to report for this week after all of last weeks action, but they have completed the following:

External drainage has been completed
Underground cabling has been done
Site fence has been installed

Here are a few pictures:







Items on the agenda for next week are as follows:

Underground rainwater tank to be installed
Frames and trusses to be delivered and installed

Here's hoping that the rain that is forecast for early in the week does not impact too heavily on the people building in Sydney!

Cheers,

CMET